January 29, 2021

Subject to Change

Below please find our development schedule. Please note the schedule is subject to change.

SOFTDEMO/ABATEMENT 7/15/2020 – 11/15/2020
DEMO 11/15/2020 – 3/1/2021
SHEETING + SHORING 2/1/2021
EXCAVATION 3/15/2021 – 9/15/2021
CONCRETE G3-10TH 10/1/2021 – 12/1/2022
CURTAIN WALL ONSITE 11/1/2022 – 9/10/2023
CONCRETE 11TH – 18TH 12/1/2022 – 2/10/2023
CONCRETE 19TH – HOTEL ROOF (35TH) 2/13/2023 – 7/28/2023
EXTERIOR FRAMING 4/1/2023 – 10/1/2023
EXTERIOR MASONRY 5/1/2023 – 12/1/2023
WINDOWS RESIDENTIAL 7/1/2023 – 1/15/2024
RESIDENTIAL ROOF 1/2/2024 – 4/1/2024
CORE + SHELL 4/1/2024
OCCUPANCY/MOVE-INS 5/1/2024