SOFTDEMO/ABATEMENT |
7/15/2020 – 11/15/2020 |
DEMO |
11/15/2020 – 3/1/2021 |
SHEETING + SHORING |
2/1/2021 |
EXCAVATION |
3/15/2021 – 9/15/2021 |
CONCRETE G3-10TH |
10/1/2021 – 12/1/2022 |
CURTAIN WALL ONSITE |
11/1/2022 – 9/10/2023 |
CONCRETE 11TH – 18TH |
12/1/2022 – 2/10/2023 |
CONCRETE 19TH – HOTEL ROOF (35TH) |
2/13/2023 – 7/28/2023 |
EXTERIOR FRAMING |
4/1/2023 – 10/1/2023 |
EXTERIOR MASONRY |
5/1/2023 – 12/1/2023 |
WINDOWS RESIDENTIAL |
7/1/2023 – 1/15/2024 |
RESIDENTIAL ROOF |
1/2/2024 – 4/1/2024 |
CORE + SHELL |
4/1/2024 |
OCCUPANCY/MOVE-INS |